Temporary sidewalk, parking and travel lane restrictions in place on State Street

Beginning today, temporary sidewalk, parking, and travel lane restrictions are in place as construction gets underway for Phase 2 of the Downtown Streetscape Master Plan.

Expect temporary closures on the west side of State Street from 12th Street north. Construction crews will work in one- or two-block-long sections, and then reopen those areas as they move north toward South Park Row. Crews will then begin working on the east side of State Street from South Park Row south to 12th Street. Phase 2 closures will be dependent on construction schedules and will be intermittent until the conclusion of the project.

Construction barricades and equipment are shown, on July 17, 2023, on State Street near 11th Street in Erie. Beginning July 17, temporary sidewalk, parking and travel lane restrictions are in place as construction gets underway for Phase 2 of the Downtown Streetscape Master Plan. CHRISTOPHER MILLETTE/CITY OF ERIE

The Downtown Streetscape Master Plan includes multiple phases on State Street from Second to 12th Streets and features curbs, ADA ramps, sidewalks, decorative lighting, soil cells, trees, landscaping, and green space. Both Phase 1 and Phase 2 encompass South Park Row to 12th Street.

Phase 1, scheduled to be completed in 2024, includes:

  • New curbs
  • Decorative lighting
  • Soil cells

Phase 2, scheduled to be completed in 2024, includes:

  • New sidewalks
  • Planter areas for new sidewalk trees
  • Decorative stamped, colored concrete installed between planter areas
  • Curb ramps that are Americans with Disabilities Act-compliant

New sidewalks will be installed along with new ADA ramps at the street intersections. Planter areas will be added with stamped colored concrete installed between the planter areas. For more information about the project, contact Rob Wernicki at 814-870-1378 or rwernicki@erie.pa.us.

);